Consider 5 periodic tasks $\tau_1, \tau_2, \cdots, \tau_5$ share two resources $R_1$ and $R_2$, as shown in the following table. Each task $\tau_i$ has its arrival time $A_i$, computation time $C_i$, period $P_i$, deadline $D_i$ and a set of critical sections. Note that a critical section is represented by [$R_j$, $st$:$ft$] which indicates $R_j$ will be accessed from time $st$ to $ft$. Suppose that the tasks are scheduled by RM and PCP.

[taskset]

Task $A_i$ $C_i$ $P_i = D_i$ Critical Section(s)
$\tau_1$ $4$ $2$ $12$ None
$\tau_2$ $0$ $6$ $25$ [$R_1$, 1:5]
$\tau_3$ $7$ $3$ $10$ [$R_2$, 1:2]
$\tau_4$ $2$ $6$ $20$ [$R_1$, 1:5][$R_2$, 3:4]
$\tau_5$ $5$ $3$ $18$ [$R_2$, 1:2]

[fig] image

[taskset]

direct PI ceiling
blocking blocking blocking
$\tau_1$ $\tau_2$ $\tau_3$ $\tau_4$ $\tau_1$ $\tau_2$ $\tau_3$ $\tau_4$ $\tau_1$ $\tau_2$ $\tau_3$ $\tau_4$ worst-case blocking time
$\tau_1$ X          X          X            
$\tau_2$    X          X          X         
$\tau_3$       X          X          X      
$\tau_4$          X          X          X   